Fiber optic patchcord FOR SALE!!


We are currently preparing for HARI RAYA CRAZY DEAL for all out fiber optic products. Below are some of the promotion price for all of our readers. Remember, this HARI RAYA CRAZY DEAL is limited to our valued blog readers.
Patchcord SM LC/UPC - LC/UPC simplex 3 meter


Patchcord SM SC/UPC - SC/UPC simplex 3 meter

Patchcord SM FC/UPC - FC/UPC simplex 3 meter

Patchcord SM E2000/APC - E2000/APC simplex 3 meter

Patchcord SM SC/UPC - SC/UPC duplex 3 meter

Patchcord SM FC/UPC - FC/UPC duplex 3 meter


More coming updates for this HARI RAYA CRAZY DEAL. Please stay visit to our blog frequently
TQ
Asrul +6013-4882800
asrul@soulcommunication.com.my

Sunday, August 8, 2010

Knowledge Part 4 : Fiber termination for FTTH

Hi to all readers.
We are proud that our little blog has received visitors from nine (9) countries including ours; Malaysia.
We always treat our blog as a knowledge platform to share with all readers out there. In this part 4, we would like to share on our experience involving in Fiber-To-The-Home termination works.

In Malaysia, this FTTH project was lead by our giant telco company, Telekom Malaysia Berhad (TM).
Below are step-by-step in performing fiber termination work for outdoor distribution panel.

Step 1 : Cutting the outer jacket of fiber optic cable

Step 2 : Remove the outer jacket of fiber optic cable

Step 3 : Pulling out the nylon rope inside the cable to the desired length

Step 4 : Pulling out the loose tube through the nylon rope line

Step 5 : Cutting out the strength member

Step 6 : Clean up the loose tube using approved cleaner and tissues

Step 7 : Put the cable end to the desired incoming cable port

Step 8 : Lock the cable and strength member with screw

Step 9 : Coil the unused / spare loose tube first

Step 10 : Strip the loose tube using the tube cutter

Step 11 : Pull out the loose tube and clean up the dark fiber

Step 12 : Setting up the dark fiber and pigtail using fusion splicing machine and splice

Step 13 : After splicing done, coil the excess dark fiber on the tray

Step 14 : Fiber termination work done and lock the distribution panel properly

Step 15 : Bring up the panel to the pole location

Step 16 : Terminate the panel using stainless steel tie onto the pole

Step 17 : Coil the cable and tie it with jubilee clip. It's done!