Photo 1 : Insert the flexitrace into the sub-duct
Photo 2 : Ensure the flexitrace inserted into spare duct
Photo 3 : Activate and calibrate the transmitter
Photo 4 : Detect the flexitrace route using the receiver unit
Photo 5 : Dig pilot hole using backhoe (to reduce time)
Photo 6 : Manually excavate to double check other utilities
Photo 7 : Finally found the manhole buried underground
Photo 8 : Found manhole cover buried about 1.2meter underground. Strange??
the last picture so damn scary... looks like someone that will bury alive @o@
ReplyDeletedalamnya tanam manhole..preventive measure ke?hehe
ReplyDeleteSalam Ihsan,
ReplyDeleteManhole ni terkambus gara-gara local authority tambak tanah....biasanya dulu kawasan ni jalan satu lane ja....sekarang dh jadi 4 lane....huhuh
hebat la company ni..
ReplyDeleteSalam En Kamal.
ReplyDeleteThanks for visiting our blog. This blog is dedicated for all visitors out there to read our experience and review our products. There are also some of our clients from Telcos called me up to learn and understand more about the fiber optic.
Anyway, we don't lost anything by sharing our knowledge....it's satisfaction by helping others..