Below here we share on one of the project which carried out in December 2011. This job was done at Taman Puteri Jaya, Sungai Petani, Kedah
Perform HDD work for 1 way PN10
The HDD starting point for boring the HDD rod
HDD machinery at site
Civil trenching along the Petronas Gas pipeline
Trenching works completed
Install warning tape 1 feet below soil level
Install new JRC7 manhole pre-cast
Install plate B at incoming duct for 3 way sub-duct
Built joint box mix on site
Rod standard duct
Site clearance. Job done !!