FIBER SPLICING WORKS AT SEPANGAR BAY POWER STATION, SABAH

Update from our daily activities :

We finished fiber splicing works at Sepangar Bay Power Station in Sabah in February 2014. The scope of works are to terminate fiber optic via fusion splicing at their Tranfix unit (a transformer gas analyser) with small FWS and ended with termination at the control room. All our manpower are fully NIOSH-TNB certified.










.






For any installation and splicing services, kindly please do drop your project inquiry to asrul@soulcommunication.com.my / 013 - 488 28000 (Asrul)

Tuesday, March 25, 2014

INSTALLATION OF OVERHEAD FIBER OPTIC CABLE AT BUKIT KAYU HITAM

Update from our daily activities:

Today we finished installation of 96 core ADSS fiber optic overhead cable via 10 meter concrete poles. This installation is part of the repair work which previously was damaged due to burnt area.












If you have any inquiry for our installation service including fiber splicing, kindly please do contact us at
asrul@soulcommunication.com.my / 013 - 488 2800 (Asrul)

Monday, March 10, 2014

INSTALLATION OF CONCRETE POLE ALONG JKR RESERVED

Update from our daily activities:

-Concrete pole installation for temporary cable diversion due to JKR project

-Area where new bridge is being built. Existing underground cable need to divert temporarily

-Tighten up the concrete pole with safety harness

-Lifting concrete pole using crane

-Temporary lifting to work area

-Concrete pole lifted at open space area

-Lifting another concrete pole

Area where concrete pole to be erec

-Using backhoe to digging hole

-Limited working space for backhoe

-Backhoe start lift up concrete pole and erect 

-Erecting concrete pole in progress

-Erecting concrete pole in progress

-Erecting concrete pole in progress

-One of the concrete poles erected at site

For those who is seeking our installation services, kindly please do contact us at 
asrul@soulcommunication.com.m / 013-488 2800 (Asrul)